Feasibility and cost-estimation rules
The general feasibility-study sequence and the instruments Pakistan's authorities use to estimate and value construction cost.
- Status
- stable
- Trust
- unverified
- Owner
- Human: Afia Bakr
- Approved
- Human: Afia Bakr ·
A feasibility study for a construction project in Pakistan has to clear four gates, roughly in this order, before a design is worth committing money to.
1. Land-use and zoning feasibility
Confirm the site's permitted use against the relevant area authority's master plan / zoning classification — residential, commercial, industrial, or a mixed category — before any design work. Every area document in this section names the authority that holds this master plan. A use that is not permitted on the plot cannot be approved regardless of design quality.
2. Regulatory approval feasibility
Identify which authority's building bye-laws govern the site (see the area documents), what NOCs are required (fire, environment, civil aviation height clearance near airports, etc. — these vary by area and are not enumerated here), and the authority's plan-approval and completion-certificate process.
3. Technical / structural feasibility
Design must comply with the applicable Building Code of Pakistan seismic provisions (see the overview) and be executed by PEC-registered engineers and PCATP-registered architects, since only registered professionals and firms may lawfully offer these services.1
4. Financial feasibility — the estimation instruments
Pakistan uses two distinct, non-interchangeable rate instruments. Confusing them is a common estimation error.
Warning
The Composite Schedule of Rates (CSR) estimates what it costs to build. The FBR valuation table / DC rate estimates what a property is worth for tax and stamp-duty purposes. Neither substitutes for the other, and neither should be used as a stand-in for a contractor's own bid.
Composite Schedule of Rates (CSR) — construction cost estimation
Each province (and AJK) publishes its own CSR, prepared by its Communication & Works / Planning & Development department, giving unit rates for manpower, materials and equipment across its districts. A CSR-based estimate applies these unit rates to quantities taken off the drawings (a bill of quantities), then adds a 25% markup on the estimated unit cost to cover overheads, taxes, preliminaries and profit — this markup figure is stated in the CSR methodology itself, not a general industry rule of thumb.2 CSR editions are dated and revised (2025 editions exist for Punjab, Sindh and KP, for example) — always use the current edition for the province of the site, never a carried-forward figure.34567
FBR valuation tables and DC rates — property valuation, not construction cost
The FBR valuation table is the Federal Board of Revenue's official per-area value for a property, used to compute capital gains tax and withholding tax on property transactions; it is published and periodically revised (most recently, per this record's research, city-wise updates dated 1 November 2024) on FBR's own site.8 The DC rate ("collector rate") is set separately by the district administration and used for stamp duty and registration fee on transfer — it is a different, usually lower, figure from the FBR rate, and both are administrative valuations rather than market price.
Professional consultancy fees
The Pakistan Engineering Council publishes fee structures for firm and individual registration/renewal — figures found in this research ranged roughly Rs. 10,000–30,000 per year depending on category — but this record has not located PEC's schedule of consultancy-service fees (commonly expressed as a percentage of project cost, banded by project type), nor PCATP's scale of professional charges for architects.19
Important
Open question: the current PEC "Schedule of Fees for Consultancy Services"
and PCATP's scale of professional charges are the authoritative source for
consultancy fee percentages. This record does not state a percentage figure
because none was found and verified — check pec.org.pk and pcatp.org.pk
directly, or add the document to this record via add-sources once
obtained.
Footnotes
-
Composite Schedule of Rates (CSR) — methodology and 25% overhead/profit markup. ↩
-
Composite Schedule of Rates (2025) — Punjab. ↩
-
Composite Schedule of Rates (2025) — Sindh. ↩
-
Composite Schedule of Rates (CSR) — Khyber Pakhtunkhwa 2025. ↩
-
Government of Balochistan — Composite Schedule of Rates, Vol. 1. ↩
-
AJK Planning & Development Department — Composite Schedule of Rates. ↩
-
Federal Board of Revenue — Valuation of Immovable Properties. ↩
-
PCATP — fee structure section (referenced, not itemised in this record). ↩
Sources
- [^csr-methodology]Composite Schedule of Rates (CSR) — methodology and 25% overhead/profit markup
- [^csr-punjab-2025]Composite Schedule of Rates (2025) — Punjab
- [^csr-sindh-2025]Composite Schedule of Rates (2025) — Sindh
- [^csr-kp-2025]Composite Schedule of Rates (CSR) — Khyber Pakhtunkhwa 2025
- [^csr-balochistan]Government of Balochistan — Composite Schedule of Rates, Vol. 1
- [^csr-ajk]AJK Planning & Development Department — Composite Schedule of Rates
- [^fbr-valuation]Federal Board of Revenue — Valuation of Immovable Properties
- [^pec-fee-structures]PEC Fee Structures — Pakistan Engineering Council
- [^pcatp-fee]PCATP — fee structure section (referenced, not itemised in this record)
Architecture planning and building control in Pakistan — overview
How building-control authority is organised across Pakistan, and how this section is structured by area.
Islamabad Capital Territory — Capital Development Authority
CDA's legal basis, regulations and resource links for building control in Islamabad.