# Feasibility and cost-estimation rules (/docs/architecture-planning/feasibility-and-estimation)

---
type: Document
title: Feasibility and cost-estimation rules
description: The general feasibility-study sequence and the instruments Pakistan's authorities use to estimate and value construction cost.
status: stable
order: 11
generated: { by: "human:afiabakr", at: 2026-09-17T16:00:00Z }
ksor:
  audience: [public]
  owner: human:afiabakr
  approval: { by: "human:afiabakr", at: 2026-09-17T16:05:00Z }
sources:
  - id: csr-methodology
    title: Composite Schedule of Rates (CSR) — methodology and 25% overhead/profit markup
    resource: https://nha.gov.pk/uploads/topics/17697464446570.pdf
  - id: csr-punjab-2025
    title: Composite Schedule of Rates (2025) — Punjab
    resource: https://www.scribd.com/document/991497856/COMPOSITE-SCHEDULE-OF-RATES-2025-PUNJAB
  - id: csr-sindh-2025
    title: Composite Schedule of Rates (2025) — Sindh
    resource: https://www.scribd.com/document/991497863/COMPOSITE-SCHEDULE-OF-RATES-2025-SINDH
  - id: csr-kp-2025
    title: Composite Schedule of Rates (CSR) — Khyber Pakhtunkhwa 2025
    resource: https://www.scribd.com/document/1029803575/Csr-Kpk-2025
  - id: csr-balochistan
    title: Government of Balochistan — Composite Schedule of Rates, Vol. 1
    resource: https://www.bppra.gob.pk/uploads/fck_uploads/CSRVol-1.pdf
  - id: csr-ajk
    title: AJK Planning & Development Department — Composite Schedule of Rates
    resource: https://pndajk.gov.pk/AJKCSR/2015-16/2nd%20Semi%20Annual%20Jan%202016%20to%20Jun%202016/Kotli/Table%20of%20Contents.pdf
  - id: fbr-valuation
    title: Federal Board of Revenue — Valuation of Immovable Properties
    resource: https://www.fbr.gov.pk/valuation-of-immovable-properties/51147/131220
  - id: pec-fee-structures
    title: PEC Fee Structures — Pakistan Engineering Council
    resource: https://www.pec.org.pk/pec-fee-structures/
  - id: pcatp-fee
    title: PCATP — fee structure section (referenced, not itemised in this record)
    resource: https://pcatp.org.pk/
trust_tier: unverified
build_id: sha256:03248cb4f5876109b77295e02982112e147139ea6f7f59e712ef9eb9ba16a7b0
source_commit: bceb092587ddbf0663b4e0976c015983c964959f
ksor_version: 0.0.58
---

A feasibility study for a construction project in Pakistan has to clear four
gates, roughly in this order, before a design is worth committing money to.

## 1. Land-use and zoning feasibility

Confirm the site's permitted use against the relevant area authority's master
plan / zoning classification — residential, commercial, industrial, or a
mixed category — **before** any design work. Every area document in this
section names the authority that holds this master plan. A use that is not
permitted on the plot cannot be approved regardless of design quality.

## 2. Regulatory approval feasibility

Identify which authority's building bye-laws govern the site (see the area
documents), what NOCs are required (fire, environment, civil aviation height
clearance near airports, etc. — these vary by area and are not enumerated
here), and the authority's plan-approval and completion-certificate process.

## 3. Technical / structural feasibility

Design must comply with the applicable **Building Code of Pakistan** seismic
provisions (see
[the overview](overview.md#the-three-tracks-that-run-in-parallel-everywhere))
and be executed by PEC-registered engineers and PCATP-registered architects,
since only registered professionals and firms may lawfully offer these
services.[^pec-fee-structures]

## 4. Financial feasibility — the estimation instruments

Pakistan uses **two distinct, non-interchangeable** rate instruments. Confusing
them is a common estimation error.

> [!WARNING]
> The **Composite Schedule of Rates (CSR)** estimates what it costs to
> **build**. The **FBR valuation table / DC rate** estimates what a property
> is **worth** for tax and stamp-duty purposes. Neither substitutes for the
> other, and neither should be used as a stand-in for a contractor's own bid.

### Composite Schedule of Rates (CSR) — construction cost estimation

Each province (and AJK) publishes its own CSR, prepared by its Communication
& Works / Planning & Development department, giving unit rates for
manpower, materials and equipment across its districts. A CSR-based estimate
applies these unit rates to quantities taken off the drawings (a bill of
quantities), then adds a **25% markup on the estimated unit cost to cover
overheads, taxes, preliminaries and profit** — this markup figure is stated
in the CSR methodology itself, not a general industry rule of
thumb.[^csr-methodology] CSR editions are dated and revised (2025 editions
exist for Punjab, Sindh and KP, for example) — always use the **current**
edition for the province of the site, never a carried-forward
figure.[^csr-punjab-2025][^csr-sindh-2025][^csr-kp-2025][^csr-balochistan][^csr-ajk]

### FBR valuation tables and DC rates — property valuation, not construction cost

The **FBR valuation table** is the Federal Board of Revenue's official
per-area value for a property, used to compute capital gains tax and
withholding tax on property transactions; it is published and periodically
revised (most recently, per this record's research, city-wise updates dated 1
November 2024) on FBR's own site.[^fbr-valuation] The **DC rate** ("collector
rate") is set separately by the district administration and used for stamp
duty and registration fee on transfer — it is a different, usually lower,
figure from the FBR rate, and both are administrative valuations rather than
market price.

### Professional consultancy fees

The **Pakistan Engineering Council** publishes fee structures for firm and
individual registration/renewal — figures found in this research ranged
roughly Rs. 10,000–30,000 per year depending on category — but this record has
**not** located PEC's schedule of consultancy-service fees (commonly expressed
as a percentage of project cost, banded by project type), nor PCATP's scale of
professional charges for architects.[^pec-fee-structures][^pcatp-fee]

> [!IMPORTANT]
> Open question: the current PEC "Schedule of Fees for Consultancy Services"
> and PCATP's scale of professional charges are the authoritative source for
> consultancy fee percentages. This record does not state a percentage figure
> because none was found and verified — check pec.org.pk and pcatp.org.pk
> directly, or add the document to this record via `add-sources` once
> obtained.

[^pec-fee-structures]: PEC Fee Structures — Pakistan Engineering Council.
[^csr-methodology]: Composite Schedule of Rates (CSR) — methodology and 25% overhead/profit markup.
[^csr-punjab-2025]: Composite Schedule of Rates (2025) — Punjab.
[^csr-sindh-2025]: Composite Schedule of Rates (2025) — Sindh.
[^csr-kp-2025]: Composite Schedule of Rates (CSR) — Khyber Pakhtunkhwa 2025.
[^csr-balochistan]: Government of Balochistan — Composite Schedule of Rates, Vol. 1.
[^csr-ajk]: AJK Planning & Development Department — Composite Schedule of Rates.
[^fbr-valuation]: Federal Board of Revenue — Valuation of Immovable Properties.
[^pcatp-fee]: PCATP — fee structure section (referenced, not itemised in this record).